Dubai snag list checklist for apartment and villa handovers
Updated 25 October 2026
A handover inspection (snagging) finds the defects in a new unit before the buyer accepts the keys, so the developer fixes them under the handover process rather than later. This checklist covers what inspectors check in a typical Dubai apartment or villa. Adapt it to the unit and the developer's handover pack.
Before you start
- Get the floor plan and the unit number, and note the date and time of the visit.
- Check power, water and AC are on: many snags only show with services running.
- Bring a moisture meter, a level, a tile-tapping tool, a socket tester and a torch. A thermal camera helps find hidden leaks and missing insulation.
Room by room
Entrance and doors
- Main door: closes and latches by itself (door closer), seals, lock and handle, fire rating label where required.
- Internal doors: alignment, gaps, hinges, scratches, door stops.
Floors and walls
- Tap tiles for hollow sounds; check lippage, cracks, chips and grout gaps.
- Paint finish under side light: patches, roller marks, stains, cracks.
- Skirting gaps and silicone at joints.
Kitchen
- Cabinet doors and drawers align and close; countertop joints sealed.
- Sink and mixer: run water and check underneath for drips.
- Cooker hood extracts; appliances (if supplied) power on.
Bathrooms
- Water test the floor: water should run to the drain, not pond.
- Shower screen silicone, wall tile grout, WC fixed firmly, flush works.
- Exhaust fan runs; hot water arrives in a reasonable time.
Bedrooms and living areas
- Windows open, close and lock; sliding door seals keep out daylight and dust.
- Wardrobe doors and fittings; ceiling cracks along gypsum board joints.
Electrical, AC and safety
- Every socket tested; switches and lights work; DB panel labelled.
- AC cools in every room, grilles fit the ceiling, no rattles or condensate leaks.
- Smoke and heat detectors present and not painted over.
Balcony and outside
- Glass balustrade clamps and handrail are tight; balustrade height looks right.
- Floor falls to the drain; drain is clear of construction debris.
- For villas: roof, external walls, garden drainage, boundary walls and gates.
What the snag report should include
- A reference number for every snag, so the developer and buyer talk about the same item.
- Where it is: room and exact location, ideally a pin on the floor plan.
- A photo and a one-line description of the defect, plus the action needed.
- Severity (safety, defect, minor) so urgent items are fixed first.
- Trade (tiling, MEP, joinery and so on), so the developer can hand each group to the right team.
See a sample snagging report with snags pinned on the floor plan, the developer list by trade and the de-snag that follows it.
Questions
- What is snagging?
- A handover inspection of a new property that lists the defects (snags) for the developer to fix before or soon after the buyer takes the keys.
- What should a snag list include?
- For each snag: a reference number, the room and exact location, a photo, a short description, the action needed, a severity and the trade responsible.
- Should the snag list be grouped by trade?
- It helps. Developers pass snags to the teams that fix them, so a list grouped by trade (tiling, MEP, joinery and so on) is quicker to act on.