Dubai snag list checklist for apartment and villa handovers

Updated 25 October 2026

A handover inspection (snagging) finds the defects in a new unit before the buyer accepts the keys, so the developer fixes them under the handover process rather than later. This checklist covers what inspectors check in a typical Dubai apartment or villa. Adapt it to the unit and the developer's handover pack.

Before you start

  • Get the floor plan and the unit number, and note the date and time of the visit.
  • Check power, water and AC are on: many snags only show with services running.
  • Bring a moisture meter, a level, a tile-tapping tool, a socket tester and a torch. A thermal camera helps find hidden leaks and missing insulation.

Room by room

Entrance and doors

  • Main door: closes and latches by itself (door closer), seals, lock and handle, fire rating label where required.
  • Internal doors: alignment, gaps, hinges, scratches, door stops.

Floors and walls

  • Tap tiles for hollow sounds; check lippage, cracks, chips and grout gaps.
  • Paint finish under side light: patches, roller marks, stains, cracks.
  • Skirting gaps and silicone at joints.

Kitchen

  • Cabinet doors and drawers align and close; countertop joints sealed.
  • Sink and mixer: run water and check underneath for drips.
  • Cooker hood extracts; appliances (if supplied) power on.

Bathrooms

  • Water test the floor: water should run to the drain, not pond.
  • Shower screen silicone, wall tile grout, WC fixed firmly, flush works.
  • Exhaust fan runs; hot water arrives in a reasonable time.

Bedrooms and living areas

  • Windows open, close and lock; sliding door seals keep out daylight and dust.
  • Wardrobe doors and fittings; ceiling cracks along gypsum board joints.

Electrical, AC and safety

  • Every socket tested; switches and lights work; DB panel labelled.
  • AC cools in every room, grilles fit the ceiling, no rattles or condensate leaks.
  • Smoke and heat detectors present and not painted over.

Balcony and outside

  • Glass balustrade clamps and handrail are tight; balustrade height looks right.
  • Floor falls to the drain; drain is clear of construction debris.
  • For villas: roof, external walls, garden drainage, boundary walls and gates.

What the snag report should include

  • A reference number for every snag, so the developer and buyer talk about the same item.
  • Where it is: room and exact location, ideally a pin on the floor plan.
  • A photo and a one-line description of the defect, plus the action needed.
  • Severity (safety, defect, minor) so urgent items are fixed first.
  • Trade (tiling, MEP, joinery and so on), so the developer can hand each group to the right team.

See a sample snagging report with snags pinned on the floor plan, the developer list by trade and the de-snag that follows it.

Questions

What is snagging?
A handover inspection of a new property that lists the defects (snags) for the developer to fix before or soon after the buyer takes the keys.
What should a snag list include?
For each snag: a reference number, the room and exact location, a photo, a short description, the action needed, a severity and the trade responsible.
Should the snag list be grouped by trade?
It helps. Developers pass snags to the teams that fix them, so a list grouped by trade (tiling, MEP, joinery and so on) is quicker to act on.