After the developer says the snags are fixed, a de-snag (re-inspection) checks each one. The buyer wants a clear answer: what is done, what is not, and what is still a safety risk.
Start from the first report
Re-inspect against the original snag list, not from scratch. Every snag keeps its reference number and original photo, so nobody argues about which defect is meant.
Three outcomes per snag
- Fixed: the defect is gone and the repair is acceptable.
- Partly fixed: work was done but the result is not acceptable yet (for example only some hollow tiles re-laid).
- Not fixed: no change. Add a new photo to show it.
Record any new defects caused by the repairs as new snags.
The de-snag report
- A summary: how many snags were re-checked and the percentage fixed.
- Open items first, safety items at the top.
- For each open item: original photo, new photo, and what is still wrong.
- A short list of what remains for the developer, again grouped by trade.
State your re-inspection policy up front
Buyers compare firms on whether a de-snag is included, how many visits, and the price of extra visits. Put it in your agreement and on your booking page.
In HandoverCheck, you start a re-inspection from the published report: the open snags come across with their photos, you mark each one in the app, and the report shows the counts and the percentage fixed.
Questions
- What is de-snagging?
- A re-inspection after the developer's repairs, checking each snag from the first report and marking it fixed, partly fixed or not fixed.
- What should a de-snag report show?
- How many snags were re-checked, the percentage fixed, and for each open item the original photo, a new photo and what is still wrong.
- Should new defects be included?
- Yes. Record any new defects caused by the repairs as new snags so the developer fixes them too.