Sample Snagging Co. (demo)
Snag list: Apartment 1204, Sample Tower (fictional), Dubai
Report #2041 ยท Unit 1204 ยท 22 open item(s) across 11 trade(s)
MEP / HVAC: 5Tiling: 4Aluminium and glazing: 3Plumbing: 2Joinery: 2MEP / fire: 1Gypsum and ceilings: 1Electrical: 1Doors and ironmongery: 1Painting: 1Civil works: 1
MEP / HVAC (5)
| Ref | Where | Defect | Photo | Fixed? |
|---|---|---|---|---|
| 4.6.1 | Kitchen Above the hob | Cooker hood not extracting (Defect / repair) The hood runs but there is no airflow at the outlet; the duct may not be connected. Developer to rectify before handover (mep / hvac). | ๐ 4.6.1 | โ Yes โ No |
| 6.7.1 | Bathrooms Master bath ceiling | Bathroom exhaust fan not working (Defect / repair) The fan does not start from the switch or the light circuit. Developer to rectify before handover (mep / hvac). | ๐ 6.7.1 | โ Yes โ No |
| 8.2.1 | Maid's / store / laundry Maid's room | No ventilation in maid's room (Defect / repair) The room has no working extract fan or vent; the fan switch does nothing. Developer to rectify before handover (mep / hvac). | ๐ 8.2.1 | โ Yes โ No |
| 3.5.1 | Living and dining Living room ceiling | AC grille not aligned with ceiling (Maintenance) The supply grille sits about 5 mm proud of the gypsum ceiling on one side. Developer to rectify before handover (mep / hvac). | ๐ 3.5.1 | โ Yes โ No |
| 5.7.1 | Bedrooms Master bedroom | AC unit rattles (Maintenance) The fan-coil unit above the master bedroom rattles at medium and high speed. Developer to rectify before handover (mep / hvac). | ๐ 5.7.1 | โ Yes โ No |
Tiling (4)
| Ref | Where | Defect | Photo | Fixed? |
|---|---|---|---|---|
| 3.1.1 | Living and dining Living room, by balcony door | Hollow floor tiles by the balcony door (Defect / repair) Four tiles sound hollow when tapped, a sign the adhesive bed is incomplete. Hollow tiles can crack under load. Developer to rectify before handover (tiling). | ๐ 3.1.1 | โ Yes โ No |
| 6.1.1 | Bathrooms Master bath | Water ponds away from the floor drain (Defect / repair) After a water test, water collects in the corner opposite the drain instead of running to it. Developer to rectify before handover (tiling). | ๐ 6.1.1 | โ Yes โ No |
| 6.5.1 | Bathrooms Master bath shower | Missing silicone at shower screen (Defect / repair) There is no silicone seal along the bottom of the shower glass; water reaches the floor outside. Developer to rectify before handover (tiling). | ๐ 6.5.1 | โ Yes โ No |
| 6.2.1 | Bathrooms Bath 2, basin wall | Gaps in wall tile grout (Maintenance) Several grout lines behind the basin are open, which lets water behind the tiles. Developer to rectify before handover (tiling). | ๐ 6.2.1 | โ Yes โ No |
Aluminium and glazing (3)
| Ref | Where | Defect | Photo | Fixed? |
|---|---|---|---|---|
| 5.6.1 | Bedrooms Bedroom 2 window | Bedroom window does not lock (Safety hazard) The window handle turns but the lock does not engage; a child could open it. Developer to rectify before handover (aluminium and glazing). | ๐ 5.6.1 | โ Yes โ No |
| 7.1.1 | Balcony Balcony, middle panel | Loose glass balustrade clamp (Safety hazard) One clamp on the balcony glass moves by hand and the panel flexes when pushed. Developer to rectify before handover (aluminium and glazing). | ๐ 7.1.1 | โ Yes โ No |
| 3.4.1 | Living and dining Balcony sliding door | Gap in sliding door seal (Defect / repair) Daylight is visible along the bottom of the balcony sliding door when closed; dust and water can get in. Developer to rectify before handover (aluminium and glazing). | ๐ 3.4.1 | โ Yes โ No |
Plumbing (2)
| Ref | Where | Defect | Photo | Fixed? |
|---|---|---|---|---|
| 4.3.1 | Kitchen Under kitchen sink | Slow leak under the sink (Defect / repair) Water drips from the waste connection under the sink when the tap runs for a minute. Developer to rectify before handover (plumbing). | ๐ 4.3.1 | โ Yes โ No |
| 6.3.1 | Bathrooms Bath 2 | WC pan loose (Defect / repair) The WC pan rocks when sat on; the fixing bolts are not tight. Developer to rectify before handover (plumbing). | ๐ 6.3.1 | โ Yes โ No |
Joinery (2)
| Ref | Where | Defect | Photo | Fixed? |
|---|---|---|---|---|
| 4.1.1 | Kitchen Kitchen counter | Open joint in countertop (Maintenance) The joint between the two countertop sections is open by about 2 mm and not sealed. Developer to rectify before handover (joinery). | ๐ 4.1.1 | โ Yes โ No |
| 5.5.1 | Bedrooms Bedroom 2 wardrobe | Wardrobe door misaligned (Maintenance) The right wardrobe door rubs the frame and does not close flush. Developer to rectify before handover (joinery). | ๐ 5.5.1 | โ Yes โ No |
MEP / fire (1)
| Ref | Where | Defect | Photo | Fixed? |
|---|---|---|---|---|
| 9.2.1 | Services and safety Entrance hall ceiling | Smoke detector painted over (Safety hazard) The detector in the entrance hall has paint over its vents, which can stop it sensing smoke. Developer to rectify before handover (mep / fire). | ๐ 9.2.1 | โ Yes โ No |
Gypsum and ceilings (1)
| Ref | Where | Defect | Photo | Fixed? |
|---|---|---|---|---|
| 5.3.1 | Bedrooms Master bedroom ceiling | Crack in gypsum ceiling (Defect / repair) A 60 cm hairline crack runs along a board joint in the master bedroom ceiling. Developer to rectify before handover (gypsum and ceilings). | ๐ 5.3.1 | โ Yes โ No |
Electrical (1)
| Ref | Where | Defect | Photo | Fixed? |
|---|---|---|---|---|
| 5.8.1 | Bedrooms Bedroom 2, bed wall | Loose socket outlet (Defect / repair) The double socket by the bed moves in the wall when a plug is pushed in. Developer to rectify before handover (electrical). | ๐ 5.8.1 | โ Yes โ No |
Doors and ironmongery (1)
| Ref | Where | Defect | Photo | Fixed? |
|---|---|---|---|---|
| 2.2.1 | Entrance and corridor Main entrance door | Main door closer not closing fully (Maintenance) The fire-rated main door stops about 10 cm short of closing by itself. Developer to rectify before handover (doors and ironmongery). | ๐ 2.2.1 | โ Yes โ No |
Painting (1)
| Ref | Where | Defect | Photo | Fixed? |
|---|---|---|---|---|
| 3.2.1 | Living and dining Living room, long wall | Uneven paint and patch marks (Maintenance) Visible roller marks and two filled patches on the long wall that show under side light. Developer to rectify before handover (painting). | ๐ 3.2.1 | โ Yes โ No |
Civil works (1)
| Ref | Where | Defect | Photo | Fixed? |
|---|---|---|---|---|
| 7.2.1 | Balcony Balcony drain | Balcony drain blocked with debris (Maintenance) Construction debris blocks the balcony floor drain; water would pond after rain or cleaning. Developer to rectify before handover (civil works). | ๐ 7.2.1 | โ Yes โ No |
In a real report, each row has the snag photo with the time it was taken, and the developer can download this list as a spreadsheet.